Free C_TS4CO_2020 Exam Braindumps certification guide Q&A


SAP C_TS4CO_2020 Exam Description:

The 'SAP Certified Application Associate - SAP S/4HANA for Management Accounting Associates (SAP S/4HANA 2020)' certification exam verifies that the candidate possesses fundamental knowledge and proven skills in the area of SAP S/4HANA Management Accounting. It tests that the candidate has a good overall understanding within this consultant profile and can implement this knowledge practically in projects under the guidance of an experienced consultant. It is recommended as an entry-level qualification to allow consultants to get acquainted within Management Accounting projects. This certificate is the ideal starting point for a professional career as a Management Accounting consultant on SAP S/4HANA. If experience in SAP implementation projects of Management Accounting are added over years, a professional career can be validated by taking a second exam which focuses on the migration from SAP ERP to SAP S/4HANA: "SAP Certified Application Professional - Financials in SAP S/4HANA for SAP ERP Financials experts".


C_TS4CO_2020 Exam Certification Details:

Cut Score:64%
Level:Associate
Exam:80 questions
Sample Questions: SAP C_TS4CO_2020 Exam Sample Question
Languages:German, English, Russian

 

NEW QUESTION 37
How does SAP S/4HANA capture costs?

  • A. Primary and secondary costs are captured in general ledger accounts
  • B. Secondary costs are captured as secondary cost elements, and NOT as general ledger accounts.
  • C. All primary and secondary costs are captured by creating them as cost elements.
  • D. Only primary costs are captured in general ledger accounts

Answer: A,C

 

NEW QUESTION 38
You want to set up budget availability control for your projects and internal ordders. What can you check using budget availability control? 2 Answers

  • A. The availability of funds on period level
  • B. The availability of funds in object currency
  • C. The availability of funds using overall plan value
  • D. The availability of funds according to tolerance limits

Answer: B,D

 

NEW QUESTION 39
Which settings can you configure per order type for the budget and availability control? There are TWO correct answers for this question

  • A. Budget tolerance limits
  • B. Budget data entry layout
  • C. Design budget manager
  • D. Budgeting on cost element level

Answer: A,D

 

NEW QUESTION 40
Which objects do you use when you assign costs and revenue to the value fields in costingbased CO- PA?

  • A. Transfer structure
  • B. Overhead group
  • C. Allocation structure
  • D. Allocation template

Answer: C

 

NEW QUESTION 41
You are using availability control in your SAP S/4HANA system. Which documents can cause the system to raise a warning message when the budget was exceeded? 2 answers

  • A. Outgoing payment
  • B. Goods issue from order
  • C. Incoming invoice
  • D. Purchase requisition

Answer: C,D

 

NEW QUESTION 42
In the material master record there are three planned prices: ""Planned price 1"", ""Planned price 2""and""Planned price 3"". What do you use them for?

  • A. To valuate the materials in cost estimates
  • B. To valuate goods movement
  • C. To update the standard price during the release of a standard cost estimate
  • D. To valuate material stocks

Answer: A

 

NEW QUESTION 43
What do you need to define in order to report variable costs that refer to the cost component split in account-based CO-PA? There are TWO correct answers for this question

  • A. A calculation formula
  • B. A cost splitting profile
  • C. A price difference profile
  • D. A variable cost field in

Answer: B,D

 

NEW QUESTION 44
You are creating new activity type and want to maintain plan prices for a cost center. Which attribute must you configure in the activity type master record? Note: There are 3 correct answers to this question.

  • A. Valid cost center categories
  • B. Company code
  • C. CO version
  • D. Price indicator
  • E. Activity type category

Answer: A,D,E

 

NEW QUESTION 45
What are some of the unique attributes of an assessment cycle in Controlling? 2answers

  • A. They use the original cost element during transfer
  • B. They transfer primary and secondary costs
  • C. They use a secondary cost element during transfer
  • D. They transfer only primary costs

Answer: B,C

 

NEW QUESTION 46
Which default values can you configure for the product cost collector? Note: There are 2 correct answers to this question.

  • A. Costing variant for preliminary costing
  • B. Result Analysis (RA) Version
  • C. Result Analysis (RA) key
  • D. Variance variant

Answer: A,C

 

NEW QUESTION 47
What does SAP/S4HANA select line-item-based data for costing based Profitability Analysis reports?

  • A. It select actual data from table CE1XXXX and plan data from CE2XXXX.
  • B. It select actual data from table CE2XXXX and plan data from CE3XXXX.
  • C. It select actual data from table ACDOCA and plan data from COSP.
  • D. It select actual data from table ACDOCA and plan data from ACDOCP.

Answer: A

 

NEW QUESTION 48
In the product Cost by Order component, what does the system calculate depending on the order status? 1 answer

  • A. Both WIP and variances or only variances
  • B. WIP at target costs or variances
  • C. WIP at planned costs or variances
  • D. WIP at actual costs or variances

Answer: D

 

NEW QUESTION 49
How can you configure the transfer price solution in SAP S4/HANA? 2 Answers

  • A. Use separate segments for each valuation
  • B. Use separate accounts for each valuation
  • C. Use separate currency types within the same ledger for each valuation
  • D. Use separate ledgers for each valuation

Answer: B,D

 

NEW QUESTION 50
You want to create alternative plan versions for your controlling area, in addition to version 000. What would you use additional CO versions for? 2 answers

  • A. To store different plan data
  • B. To store actual-plan variance
  • C. To store parallel valuation
  • D. To store different budget data

Answer: A,B

 

NEW QUESTION 51
You want to determine which operations of the oruting should be considered in a product cost calculation. How do you do this ? 2 Answers

  • A. By marking the cost indicator in the control key assigned to the operation
  • B. By marking the Relevance to Costing indicator in the operation
  • C. By defining a usage key in the header of the routing
  • D. By assigning a cost center top the work center in the operation

Answer: A,B

 

NEW QUESTION 52
What do you do to create a primary cost component split? There are TWO correct answers for this question

  • A. Assign a cost component structure to the CO-version
  • B. Enter split activity prices manually
  • C. Use the cost splitting tool on cost centers
  • D. Run an activity price calculation

Answer: A,D

 

NEW QUESTION 53
How does SAP S/4HANA capture costs? Note: There are 2 correct answers to this question.

  • A. Primary and secondary costs are captured in general ledger accounts.
  • B. Secondary costs are captured as secondary cost element, and not as general ledger accounts.
  • C. Only primary costs are captured in general ledger accounts.
  • D. All primary and secondary costs are captured by creating them as cost elements.

Answer: A,D

 

NEW QUESTION 54
Which of the following objects can be selected in templates for activity-based costing? Note: There are 2 correct answers to this question.

  • A. WBS element
  • B. Internal order
  • C. Business process
  • D. Cost center/activity type

Answer: A,B

 

NEW QUESTION 55
You want to prevent reporting extreme periodic fluctuations in your P&L statement. Which Management Accounting activity should you choose to help spread irregular expenses throughout the fiscal year?

  • A. Periodic reporting
  • B. Accrual calculation
  • C. Budget availability control
  • D. Indirect activity allocation

Answer: B

 

NEW QUESTION 56
Which scenarios can be covered by the costing run?

  • A. Inventory cost estimate of all the materials in one plant
  • B. Standard cost estimate of all the materials in all plants of a controlling area
  • C. Current cost estimate of all the materials in all controlling areas
  • D. Product cost collector cost estimate in one plant

Answer: B,C

 

NEW QUESTION 57
......

C_TS4CO_2020 Certification Overview Latest C_TS4CO_2020 PDF Dumps: https://actualtests.vceprep.com/C_TS4CO_2020-latest-vce-prep.html